Thursday, January 31, 2019

OC Transpo refusing to publish performance reports due to LRT construction

Today I went to the OC Transpo website to find information about recent performance of the transit utility, and was surprised to see that they hadn't published an Annual Performance Report since 2014:



At first I wrote it off as an administrative oversight--I assumed that they had simply forgotten to upload the reports for the last few years, so I used Google to try and find the reports in case they were uploaded to the city's website or some other source.

Instead, through an official response to an inquiry from former Rideau-Rockcliffe Ward councillor (and soon-to-be National Capital Commission CEO) Tobi Nussbaum, I discovered that OC Transpo was intentionally withholding the information. Councillor Nussbaum's inquiry, submitted in February 2018, was as follows:
"I was not able to locate OC Transpo Annual Performance Reports after 2014 either in the documents records of the Transit Commission or on the OC Transpo website. Were Annual Performance Reports prepared for 2015, 2016 and 2017? If so, can these reports be posted on the OC Transpo website? If not, could staff please provide updated statistics for all of the figures measured in the 2014 Annual Performance Reports through to 2017."
In response, in June 2018, officials from OC Transpo said this (emphasis added):
"Annual performance reports have not been published for 2015, 2016, or 2017, as operations have not been comparable to the previous years because of the effects of construction of O-Train Line 1, the Confederation Line. Staff continue to monitor and track key performance measures to identify system changes and proactively make improvements where required, and where resources are available.
"Staff will be developing a new performance reporting dashboard following the transformation of OC Transpo into a multimodal system with the opening of O-Train Line 1, the Confederation Line, which will be based on current best practices in the transit industry."
This, to me, is an unsatisfactory response. Impacts on service levels as a result of LRT construction was to be expected, but that doesn't mean OC Transpo can simply not issue reports to the public. In fact, these reports could have provided valuable context and qualitative explanation to the service impacts that transit users are witnessing every day.

Along with their response, OC Transpo included a table outlining a series of performance data metrics related to customer relations, ridership, operations and maintenance, safety and security, and financial indicators.

There aren't many revelations in the performance data, but a few things stand out:

  • Ridership declined again in 2017 to 95.5M trips, the lowest number since the transit strike cratered ridership in 2009.
  • On-time performance is flagging, likely due to the effects of LRT construction; 13% of morning peak-period regular-service buses are more than 5 minutes late (18% for Connexion), and 29% of afternoon peak-period regular-service buses were more than 5 minutes late (31% for Connexion).
  • No ratings for overall satisfaction were published for 2015, 2016 or 2017--I'm not sure if they didn't ask customers or if they simply didn't want to release the information, but the gap certainly stands out.
  • The rate of mechanical failures per 100,000 vehicle kilometres where service was fully cancelled has gone up pretty significantly, to 11.4 in 2017 from 7.3 in 2014. I haven't seen coverage of this, so I'm unsure whether it's simply bad luck or if there are some red flags leading to these problems.
  • The revenue-cost ratio, or percentage of operating costs paid by transit users, remains at 50%.
The full three-page table, from OC Transpo's official response, is below (click to enlarge):




Wednesday, June 15, 2016

Transit Commission approves LRT-ready fare table, including 9% regular pass hike

At their meeting on Wednesday, the City of Ottawa's Transit Commission approved OC Transpo's proposed fare table, which is to take effect on January 1, 2017 and prepare riders for the transition to light rail in 2018.

The proposed fare table, illustrated below along with existing fares and the changes that would accompany it, will go to full council on June 22. (Click the image to enlarge it.)

*Express fares are being eliminated, and express riders will pay regular fares as of Jan. 1
**The existing Student pass will be rebranded as a Youth pass

You will notice some massive reductions in the express fares and passes, which is because OC Transpo has proposed eliminating premium express fares even though it is expected that express buses will continue to run until LRT is online. The elimination of those premium fares would have resulted in a $6M revenue shortfall for OC Transpo, which is the main reason why regular passholders will see an increase of nearly nine percent over today's pass cost.

(Note: The overall increases illustrated above, if approved, will be implemented in two phases; there will be a 2.5% increase on July 1 that was part of the 2016 budget, and the rest will take effect on Jan. 1, 2017 if approved by council.)

Paper tickets will also be discontinued as of Jan. 1, 2017, meaning the only single-fare options are cash and Presto.

Regular riders will take a big hit on their fares if they buy a monthly pass, but those who pay-per-ride with their Presto card will take an even bigger hit: Regular Presto fares will go up more than 16 percent over today's cost.

Cash fares, on the other hand, are being REDUCED, to the point where they are barely more expensive than epurse fares. This seems like a strange choice given that a major motivator for OC Transpo switching to Presto was the additional handling costs associated with cash fares (which will now, presuming they're more than five cents per fare, be subsidized by other riders).

The biggest hit, though, will be to Daypasses, which are going up by over 20 percent to hit the $10 mark on Jan. 1. It's tough to know who this will impact specifically; although Daypasses are good for families taking weekend trips, they're not marketed very heavily and thus don't seem to be used very often. Right now the Daypass is slightly cheaper than three single fares in a day, but with the hike it will only make sense if you've got four rides planned in a day.

Wednesday's commission meeting also featured a lively discussion of the proposed Low-Income Transit Pass, which the Transit Commission wants the province to pay for. Proponents of the pass, however, argued against "passing the buck" to the provincial government and made proposals to fund it by increasing fares on the existing ridership base.

Monday, February 9, 2015

Inside the Confederation Line train mock-up


Over the weekend, I made a visit to Lansdowne Park to check out the mock-up of the new Alstom Citadis Spirit light rail vehicle that will be servicing the future Confederation Line. The length of the mock-up is about a third of a "car", but it's enough to get an idea of what you will be riding in 2018.

Each set of doors has a green button on both sides to open allow passengers to enter and exit. During the winter and summer months, opening the doors only as necessary will help reduce the cold or warm air coming in at outdoor stations.



The blue and dark square pattern of the seats appears to be consistent with the colour scheme of the seats on the O-Train Bombardier trains. Cooperative seating is faced sideways with all of this spacious standing room in between. Each car will have four areas for mobility devices.


The aisle looks wide enough for people to squeeze by to exit or find a seat. But if you go further down the train (in either direction), the aisle narrows to a similar width as an articulated bus aisle before the bend.


When a train is full during rush hour, passenger flow will be a challenge. Getting by someone or allowing someone to get by you will feel uncomfortable just like on an articulated bus. Dwell times will be longer during rush-hour anyway, but poor passenger flow will only make them longer.


Below, this area has few poles to grab onto if you do stand. The lack of an overhead horizontal bar will only create pockets of unused standing space where there are no vertical bars. One can hope that an overhead bar can be added later.



If there's one thing that wasn't overlooked, it's the safety features. Each car will have six passenger intercoms for emergency use.


Right above the intercom is a message screen for displaying station names, public service announcements, and emergency messages. These messages will also be shown overhead at the accordion part of the train.

At the top, there's an emergency door release and right across, also near a set of doors, a security camera is installed.

These are only my initial observations of a model, which can't be compared to a moving train with passengers on board. You can view and step inside the mock-up on any day of the week from 8 a.m. to 8 p.m. in the Aberdeen Pavilion at Lansdowne Park until March 31.

(Correction: The mock-up will be displayed until March 31st, not "until mid-March" as initially written on OC Transpo's page.)

Thursday, September 11, 2014

Name that line

2018 O-Train system

Update (September 17): At the Transit Commission meeting today, OC Transpo confirmed the line colours on the map will be used in wayfinding signage (via the Ottawa Sun):

The Confederation Line will apply to the east-west LRT currently under construction. It will also be referred to as the 1 Line and have red wayfinding signs.

The Trillium Line will become the existing north-south diesel train service (currently called the O-Train). It will be referred to as the 2 Line and wayfinding signs will be green.

There are only two lines, but an early adoption of a numeric system for public use is a good idea. One, the public may very well refer to the lines by their numeric names for simplicity. And two , when there are more lines in the future, it's a bit of a challenge to number them many years later, which was exactly what the TTC in Toronto did this year, and have the public learn what number is associated with which line. 

OC Transpo is currently using red and green to identify bus routes as regular fare peak-hour and premium fare "express" peak-hour, respectively. To distinguish the modes of transit services from each other, different colours may be needed for the rush-hour bus services. Red and green signs inside rail stations with bus connections are not particularly useful if the rush-hour bus service continues to use the same colour scheme.


OC Transpo's rail system in 2018 will be called "O-Train", according to a report to the Transit Commission. The two rail lines in the network will also have names. The report recommends that the project name "Confederation Line" to also be the name of the east-west line and "Trillium Line" to replace "O-Train" as the name for the existing north-south route. Currently, the "O-Train" name is typically used to identify the type of transit vehicle, rather than the rapid transit line.

The "Confederation Line" name seems to have had the public's support from the very beginning. One has to wonder if this was the name all along and it was floated out before construction started to see how the public would react to it.

Labeling lines with names is supposed to minimize confusion among passengers. Interestingly, the 2018 map of the rail system above shows the "Confederation" station name on the exiting north-south line. Confederation station on the Trillium Line is not a stop to transfer to the Confederation Line, but the stop name implies it does. A different name is needed.

The report states the new name of the north-south line has to be easy to read, pronounce in both English and French, and be clear and unambiguous. After city staff reviewed some candidates for the new name, they decided "Trillium Line" fit the bill. "Trillium Line" will be introduced into the OC Transpo lexicon sometime within the next four years.

In addition to the name identities, the map of the 2018 O-Train system labels the lines by number and colour. The presence of the number names on the map may be a hint that red 1's and green 2's will appear on other customer information such as wayfinding signage at stations, especially at Bayview, the only station where the two lines meet. On the other hand, there are still four years away from the opening of a second line, so the numbering system may turn out to be nothing more than an idea.

Friday, December 27, 2013

Construction update: Downtown tunnel eastern portal, Dec. 2013

On Boxing Day, I made my way to the University of Ottawa's Simard building to snap a few photos of the construction progress of the eastern portal of the downtown light-rail tunnel. Our last set of photos were taken in late October.




Wooden roof structures are in the process of being built. On the left, an additional piece lays on its side.




More skeletal roof.



It's not the best view, but a bit of the actual tunnel entrance can be seen. Also, construction crews will have to be careful of the pool of water.

That's all for now. For updates on the construction work, if you haven't already done so, check out the light-rail project website, ottawalightrail.ca.

Sunday, December 8, 2013

Fare-paid zones proposed for major transfer stations

On Monday, the Transit Commission will be presented with the new fare strategy, proposed by OC Transpo, for Confederation and O-Train lines. The report suggests fare gates or turnstiles, fare vending machines, and electronic customer service boxes to be installed at rail station entrances.

As part of the fare plan, OC Transpo wants to implement fare-paid zones at major transfer and terminus stations. A fare-paid zone is an area where customers have already paid and are not required to further validate their fare in the station. The idea behind fare-paid zones is to make bus-rail connections as smooth as possible with minimal transfer delays for passengers. It means all-door boarding on buses, even on regular-sized 40-foot buses. Fare-paid zones are similar to the current POP areas at O-Train stations except that passengers won't be asked for proof of payment.

The proposed stations to have the fare-paid areas are Tunney's Pasture, Bayview, Greenboro, Hurdman, and Blair. A case could be made to include St. Laurent on that list since the station would already be designed to easily allow a fare-paid zone. The only pedestrian access on the upper level is the crosswalk to the shopping mall, which can controlled by fare barriers. Unless OC Transpo wants to keep the St. Laurent sales centre open, there's really no reason not to have a fare-paid zone.

For those walking off the street to take the bus at one of these stations, they will have to pay at a fare barrier before stepping onto a bus platform. When fare payments are being made outside the bus, in theory, boarding times should be reduced.

The City's concept diagram of the future Tunney's Pasture LRT station shows bus platforms as being part of the fare-paid zone:



There are a few other things to note about the proposed revamped fare system. The current time-based transfer system would still be applied to all rail stations. Barcodes on transfers are suggested to make transfers readable to fare machines. Presto cards will continue to be used. In the document, the City provides this quick-reference table on how each fare method will be used across the transit system:


Friday, December 6, 2013

Ottawa's upcoming $72M investment in transit-oriented development

According to the Ottawa Citizen, the City of Ottawa is budgeting to spend about $72M in order to provide adequate water, sewer, road, and electrical services to three east Ottawa Confederation Line stations in order to enable the level of transit-oriented development that city staff are envisioning around the light rail stops.

The stations included in this $72M investment (as I'd like to think of it) are Lees, Hurdman, and Blair. The biggest price tag within that overall envelope is an estimated $25M to improve cycling infrastructure around and connecting to the stations, which seems like a wise concept that might allow people living and working in the area to forego personal automobiles in favour of cycling and transit (and, if the visions of progressive citizens become reality, bike- and car-sharing when necessary).

From the Citizen:
Lees, on the edge of the University of Ottawa campus, needs the least work: a mere $11 million, much of that in upgraded electricity service.
Hurdman, just across the Rideau River but practically isolated with fields on three sides (thanks to its location amid old closed landfills), needs the most: $35 million, with sewer pipes making up $15 million.
Blair, much farther east, needs $26 million worth of work, and the single biggest chunk of that is $13 million to improve the almost nonexistent bike routes to and from a station that’s tucked between the Gloucester Centre mall and a Highway 174 overpass.
I consider this a $72M investment, rather than an expense, because of the long-term benefits that would come as a result of encouraging higher-density and less car-dependent living around transit stations, and it seems likely that development charges around these stations may be able to recoup some of the costs. It's good to see the city putting money where their mouths are when discussing transit-oriented development, and hopefully developers and businesses also recognize the benefits of building in the vicinity of major rail stations.

Thursday, December 5, 2013

Fare vending machines recommended at rail stations

A fare machine at a Skytrain station in Vancouver (Dan Udey/Flickr)


Earlier in the week, a City document submitted to the Transit Commission stated that fare barriers are recommended to be installed at O-Train and Confederation Line stations, starting in 2016. Other fare-related machinery, such fare vending machines and audio-visual communication posts linking to customer service representatives, are also proposed at the same rail stations, the report says.

Fare vending machines, to be placed near the fare barriers, will handle a number of transactions including the purchase of single-ride tickets, Presto monthly passes (hopefully, it can be used instantly), "companion fare", multiple-ride tickets, day passes, and "multiple-day" passes. The multi-day pass appears to be a new type of fare. It will certainly benefit tourists visiting for the weekend or staying for week(s) during events like Bluesfest or Winterlude.

The machines, which will handle cash, credit, debit, and Presto cards, have the ability to issue a Presto card and refill its e-purse. Each station entrance will have at least two fare vending machines. Parliament Station is proposed to have eight of them, the most out of all the O-Train and Confederation Line stations.

Displaying transfer times and e-purse balances on vending machine screens was not stated in the document. There should be an entirely different machine, maybe Presto specific, that simply displays this information. One can only hope.

If there is a fare-related issue, OC Transpo wants light-rail customers to use "customer help points", which are audio-visual communication posts that link to customer service representatives, located outside the fare-paid area. Due to higher operating and capital costs, face-to-face customer service from collector booths is not recommended in the plan. You have to wonder what this means for the future of the St. Laurent sales centre on the upper level.

The idea of fare vending machines being available at each Confederation Line and O-Train station must be a relief to those who wait in lengthy line-ups at the Rideau Centre.

Tuesday, December 3, 2013

Confederation Line & O-Train fare barriers to be tested in 2016

Fare gates at an MBTA station in Boston. (Dan4th Nicholas/Flickr)

As part of a new fare "control strategy", OC Transpo recommends the installation of fare barriers at Confederation Line and O-Train stations. In a report to be debated at the Transit Commission meeting next week, the implementation of fare-related equipment including fare gates, fare vending machines, and customer service communication posts, is estimated to cost between $20 and $25 million.

Physical fare barriers at O-Train stations, which are to be sheltered with "weather-protected enclosures", will be tested in 2016 before the Confederation Line opens. The decision between automated gates and turnstiles has not been made yet. The advantage to automated gates is that anyone can go through them including those who use wheelchairs or strollers.

In addition to acting as fare collectors, fare gates can be used for crowd control purposes like on Canada Day or during an emergency. The plan is to have them monitored and controlled by OC Transpo control centre. The remote ability to lock the gates is useful when there is an expected or unexpected service shutdown, for example. No one wants to pay their fare only to find out that train service isn't running.

With this method of fare collection, there is no need for POP (proof-of-payment) checkers on board any train. While it's not stated in the report, double-deckers and articulated buses will presumably continue to be inspected under the POP system.

Monday, December 2, 2013

Transitway stations get makeover in the form of "station domination"

If you travelled through Hurdman or Lincoln Fields Stations in November, you may have noticed the large Rogers Communications ads covering Transitway shelters and stairs. Pattison Outdoor Advertising, the agency in charge of managing ads on OC Transpo property, says the "station domination" ad campaign will end this week on December 3rd. (There's a photo of Hurdman Station blanketed in Rogers advertisements in the link.) Station domination gives a company exclusive advertising rights to a particular station for a limited time.

A passenger tweeted a photo of a set of stairs that shows the Rogers promotions at Lincoln Fields Station:



Last year, large lobsters were placed on top of bus stop shelters to promote P.E.I tourism. The conventional ads are the posters placed inside and outside buses, and on bus stop shelters. A single ad can wrap the entire exterior of buses. We are used to this on our transit system and wouldn't think twice. Now for the very first time in Ottawa, transit station shelters, walls, and floors can be covered in ads promoting the same message. Station domination is a common advertisement practice in subway and LRT stations across this country, but is generally met with public disapproval.

Some passengers may be annoyed with them, especially the telecom ones, while others may not noticed or simply don't care. When ads start to creep into areas that have remained ad-free, they usually don't go away. Station domination could appear in future Confederation Line stations, which will be far more spacious than the current Transitway stations and consequently, provide more opportunities to advertisers.

However, advertising on transit property is not a significant source of revenue for OC Transpo. Advertising on transit shelters and vehicles generates approximately $3.3 million per year, a relatively small amount compared to the $218.6 million revenue that the the transit agency estimates it will generate in 2014. It's roughly 1.5%. As for revenue from station domination, in 2011, the City projected it would bring $50,000 in revenue during the first year (2011) of implementation. It's nowhere near enough to stop annual fare hikes unfortunately.

Whether you like it or not, station domination is probably here to stay. There is concern about multiple ads of similarity interfering with wayfinding signage and confusing the casual user or tourist. And of course, station domination can turn a beautiful rail station into a marketing jungle. The first set of ads haven't created a public outcry, but it doesn't mean they are accepted either. Like the bus wraps, station domination should be applied sparingly.

Saturday, November 30, 2013

Coffee and comfort for riders, extra revenue for OC Transpo


Some years ago, I proposed the idea of a bar car on Ottawa's trains as a way of recouping operating costs on the upcoming light-rail system--a bar car, of course, is a car on the train that offers drink service for riders. There's definitely a potential for revenue in the system, especially once Ottawa's LRT system grows out beyond the first phase from Tunney's Pasture to Blair.

But bar cars aren't everything; you can avoid the questions of licensing and still make money (potentially far more money) by operating a café car on trains--which is what happened earlier this month in Switzerland, where a Starbucks location recently moved into a train. From Fast Company:
"Starbucks locations already seem to be everywhere you look. But starting November 21, the company will take on a new frontier: trains. Starbucks, with the help of Swiss train company SBB, has converted a double-decker car running from Geneva Airport to St. Gallen in Switzerland into a fully functional Starbucks store, complete with wood tables, leather chairs, and, in another first for the company, waitstaff."
The train route in question, from the Geneva Airport to Saint Gallen, is a four-hour trip each way; the long haul and lower passenger count probably makes installing a café in a train car a slightly simpler proposition than, say, doing it on a Confederation Line train. But there's no reason why it couldn't be done in Ottawa.

There are plenty of questions about it, including how you'd have people line up and, after receiving their drinks, how you'd get them out of the way. Plus a café car raises the spectre of spills and resultant burns, a potential lawsuit waiting to happen. But maybe a discussion with Tim Horton's or some other local coffee chain would be a good way to start assessing the feasibility of the idea.

Thursday, November 21, 2013

Flaherty not in favour of national transit strategy

Although it likely comes as no surprise, Finance Minister Jim Flaherty--the member of parliament who holds the purse strings for the federal government--is not in favour of a national transit strategy to offer predictable funding to municipalities for public transit projects.

Flaherty was recently quoted in the Edmonton Journal about a project taking place in Alberta's capital on the issue:
"Quite frankly, I’m not a big fan of fancy, big national programs. I’d much rather take the approach we’ve been taking, and deal with the City of Edmonton … deal with the various municipalities."
So far, that strategy has worked fairly well for Ottawa, as the city has received $600M in federal funding for the $2.1B Confederation Line LRT project. However, it also means that the city--as well as other cities across Canada--are forced to plan transit blindly, designing systems they'd like under the assumption that the federal government might offer one-time funding for it. We're seeing that right now with Ottawa's Stage 2 draft transit plan, which has a price tag of about $2.5B and therefore expects the federal government to come forward with another $830M or so--roughly one-third of the overall cost (the remaining two thirds, in line with past funding agreements, would be split equally between the city and the Province of Ontario).

A national transit strategy was a campaign promise of both the NDP and Liberal parties in the last federal election (the NDP even tabled a motion to establish one), and it's something very strongly supported by the Federation of Canadian Municipalities (FCM). The idea behind the strategy would be to commit dedicated funding in the annual federal budget that would be invested in eligible transit-related projects. Ideally, it would provide more predictable funding and make municipalities more able to plan transit projects thanks to the guaranteed funding.

Canada is, according to FCM, the "only OECD country without a long-term, predictable federal transit-investment policy."

Monday, October 28, 2013

Construction update: Downtown tunnel portals, Oct. 2013

Yesterday, I checked out the construction progress of the downtown tunnel portals. We've shown photos of the construction sites taken in July, and in early and late September, most of them of the western tunnel entrance. In this construction update, both portals are featured and they were photographed on October 27, 2013.

Western Portal


One of the project signs near the western portal faces Albert Street:



A look westwards from the tunnel entrance:




Eastern Portal

Some close-ups of the trench:





The view from the fifth and fourth floors of the University of Ottawa's Simard building:




I'll post more photos in an update once the roadheaders are put to work.

Friday, October 11, 2013

New-look Confederation Line website provides construction updates

OttawaLightRail.ca


The official Confederation Line website was re-designed recently and is now providing updates on the construction progress.

Here's their update for this week:

West Portal

  • Removal of blasted rock and grubbing continues.
  • Assembly of the first roadheader is completed.
  • Blasting to excavate the ramp is completed.
  • Excavation with hoe ram is scheduled to be completed by October 9.
Central Shaft

  • Excavation continues.
  • Installation of caissons continues for the foundation of the gantry crane
  • Blasting at the central shaft is scheduled to begin by end of the week.
 East Portal

  • Surface excavation of the construction ramp continues.
 Highway 417

  • Sewer and storm sewer work continues along the length of the highway.
  • Advanced Traffic Management System (ATMS) work, including temporary poles and aerial wires, continues along the highway.
  • Removals of retaining walls and bridge work continues along the highway.
 MSF

  • Demolition is scheduled to be completed by end of the week, with the exception of 737 Belfast Rd.
  • Grubbing and material removal off-site continues.

Thursday, October 10, 2013

Transit corridors that are no longer considered priorities

The newly proposed light-rail projects, named "Stage 2", in the 2013 Transportation Master Plan draft lead the transit discussion. To make room for these new initiatives, some project ideas in 2008 had to be dropped from the plan or moved beyond 2031. A comparison between the 2013 and 2008 maps will determine which transit corridors are no longer a priority.

Current 2013 proposed 2031 "affordable" transit network map:


From 2008, the 2031 transit network map:


(The links above open full-sized maps in PDF format.)

In Orleans, the Cumberland Transitway doesn't seem to be a priority anymore with the newly proposed Confederation Line extension into the eastern suburb. In 2008, the plan for Orleans was to have two busways, one grade separated along Regional Road 174 and one along Innes, both to Trim Road. Five years later, the new plan is to have light-rail extended from Blair to Place D'Orleans along Highway 174 and transit priority measurements (bus lanes, transit signal priority at intersections) on Innes Rd, Blackburn Bypass, and Brian Coburn Blvd.

The Innes Road/Industrial Avenue BRT, west of Orleans, from the 2008 plan is completely removed from this year's draft. The busway would have been parallel to the Confederation LRT Line, acting as a secondary east-west rapid transit corridor.

While the O-Train line is still planned to be extended to Bowesville, it will no longer reach Limebank as envisioned in 2008 and a rail link to the Ottawa International Airport has been removed too. Improved transit service to and from the airport is expected to happen by 2031 when HOV lanes are implemented on the Airport Parkway.

Heron/Walkley/Russell/St. Laurent was once a suggested route for bus lanes, but that's been removed from the current draft plan. St. Laurent Blvd will instead receive transit priority signals and queue jump lanes at some intersections.

Carling Avenue will no longer be a priority for rail of any kind and instead, bus lanes will be in place from the O-Train station to Lincoln Fields Station. There was a lot of discussion about Carling Avenue as an alternative route to the Sir John A. MacDonald Parkway for light rail. Or perhaps, the corridor would be served by a tram or streetcar of some sort with more local stops. For the next two decades though, it's strictly buses.

A Transitway linking Baseline Station to the Barrhaven Transitway will have to wait after 2031.

In Barrhaven, the Transitway was supposed to get an extension southwards eventually from Barrhaven Centre to Cambrian and another one eastwards along Chapman Mills across the Strandherd-Armstrong bridge, which isn't complete yet, to the previously proposed terminus of the O-Train line at Limebank Road. That was the idea five years ago and today, the plan is to have a combination of bus lanes and other transit priority measures on the same east-west route connecting Barrhaven with Riverside South.

The Kanata North Transitway will no longer be constructed northwards to Maxwell Bridge and instead, it will end at Carling Avenue. The Kanata Transitway, which was planned to run north along Highway 417 from Moodie to Huntmar and dip south between Stittsville and Kanata to Fernbank Road, is removed entirely from the 2013 plan. There are no transit priority measures of any kind in place of it.

In the news: Ottawa's proposed Transportation Master Plan


The City of Ottawa's proposed Transportation Master Plan was released publicly earlier in the week, and it features light-rail extensions from the current Confederation Line spine to Bayshore, Baseline, Bowesville, and Place D'Orleans (plus a whole bunch of other stuff complementing those extensions). Such a massive and ambitious project is rare for our usually conservative and glacially-paced city, so it should come as no surprise that the TMP is receiving ample media coverage--including prominent front-page coverage in all three local dailies:




Here's a quick look at what some people are saying:

General coverage

David Reevely, Ottawa Citizen:
"Hoping to position himself as a transportation visionary before next year’s civic election, Mayor Jim Watson announced major changes to the city’s master plan for transit, roads and cycling Wednesday morning that would extend rail west, south and east by 2023. 
"It would also handcuff the city’s transit spending for 25 years after that, and it relies on charging buyers of new homes and offices a lot more in development levies than they’re used to paying."

Jon Willing, Ottawa Sun:
"A $3-billion expansion of Ottawa's rail system can happen in 10 years with the help of upper-tier governments, a 2.5% annual property tax increase and inflationary increases to transit fares, Mayor Jim Watson said Wednesday."

Steve Collins, Ottawa Metro:
"Light rail emerged Wednesday as the showpiece of the city’s new Transportation Master Plan, with an ambitious $2.48-billion proposal to add 35 km of rail and 19 new stations."
Matthew Pearson, Ottawa Citizen: Collected initial reactions from local federal and provincial politicians, including John Baird, David McGuinty, Lisa MacLeod, Glen Murray, and Yasir Naqvi.

Mark Brownlee, Ottawa Business Journal
Catherine Kitts, Orléans Star
CBC News


Opinion

Joanne Chianello, Ottawa Citizen:
"In an unusually pre-hyped speech Wednesday morning, Watson not only laid out his vision for transit expansion in the capital but signalled what will undoubtedly be one of his major re-election platform planks: expanded rail. 
"Instead of eking rail service out across the city over the next two decades (or more), Watson opted for the bolder move of extending service to the east, west and south simultaneously in a single $3-billion project he says can be completed between 2018 and 2023. [...] 
"Watson’s plan is a brilliant tactical move, not only because it’s actually a great idea to fast-track rail — finally! — but there’s almost no political downside."

Susan Sherring, Ottawa Sun:
"Under Watson's plan, the cost of the light-rail portion of the plan is roughly $3 billion, requiring about $1 billion each from the city, the province and the feds. 
"That is problematic on many levels. 
"How likely is it either the province or the feds are going to belly up to the bar — all in?"

Eric Darwin, West Side Action:
"Mayor Jim made a big deal of his success on the Confederation Line project by having a budget first, then build to the budget (rather than design the best line, and figure out how to pay for it). He praised his initiative in bringing in this new budgeting system, and announced other cities are copying it. (Having just read Margaret Thatcher’s biography, I recall that she fought the same battle in the 1980′s in Britain and was roundly vilified for it. Maybe Jim will do better; it is, after all, 30 years later.)"

Many transit initiatives planned to be implemented by 2031

On Wednesday morning, Mayor Watson announced the City of Ottawa’s proposed transit network plan which includes the eastern extension of the Confederation Line to Place D’Orleans, western extension to Bayshore, southern extension of the O-Train line to Bowesville, all at a cost of $2.5 billion and to be completed by 2023. 

Although there doesn't seem to be any timeline attached to each project, the costs of the proposed light-rail projects were revealed in the updated TMP draft (page 38 on document, 42 on Adobe Reader):

  • O-Train southern extension from Greenboro Station to Bowesville with new stations at Gladstone, Walkley, South Keys, Leitrim, and Bowesville: $99 million. No station or connection is planned at the Airport.
  • Western LRT extension of the Confederation Line from Tunney’s Pasture to Baseline Road along existing Transitway corridor: $980 million. This proposed project was already being discussed at city hall well before the updated TMP.
  • Western LRT extension from Lincoln Fields to Bayshore in a tunnel underneath Connaught Avenue: $396 million.
  • Eastern LRT extension of the Confederation Line from Blair Station to Place D’Orleans: $500 million.
These figures are in 2013 dollars. So, in a few years, the prices of these projects will probably increase with inflation.

Buried in the draft of the Transportation Master Plan are some non-LRT transit initiatives. Here are the "affordable" BRT ones that can be implemented by 2031: 
  • Western Transitway extension from Bayshore to west of Moodie Drive will run along Highway 417 with one station near Moodie Drive. This busway, from the original TMP of 2008, is priced at $79 million.
  • Bus-rapid transit (BRT) along Baseline Road from Heron to Baseline Stations. This is a new BRT line to be constructed on the existing road with at-grade intersections and is priced at $131 million.
  • A Kanata North at-grade BRT Transitway will follow March Road, connecting Highway 417 to Carling Avenue. Kanata’s first busway will cost $110 million. This western busway was also in the 2008 TMP.

According to the next page, the number of Airport Parkway lanes will double from two to four from Hunt Club to the MacDonald-Cartier International Airport. The new lanes will become HOV lanes, but buses can only use the lanes during peak periods. The expansion is scheduled for construction between 2026 and 2031, as per the appendix.

Further down the same page, the draft of the TMP also lists some roads that can potentially feature new bus lanes:

  • Carling Avenue from the Carling O-Train Station to Lincoln Fields Station. It’s currently being served by routes 6, 16, 85, 101, 102.
  • Hemlock Road & Codd’s Road from St. Laurent Boulevard to Montreal Road. There is currently no service on these sections of roads.
  • Hunt Club Road from Albion Road to Uplands Drive. It’s currently being served by routes 1, 87, 98, 114, 116, 143, 146, 147, 189, 199.
  • Montreal Road from St Laurent to Blair Road.  It’s currently being served by route 12. The hours of the existing priority lanes form Cummings Bridge to St Laurent Blvd are to be extended.
  • Blackburn Bypass peak period lanes.
 
Here are some streets that are supposed to have both queue jump lanes and transit signal priority at selected intersections in the future:
  • Baseline Road from Baseline Station to Bayshore Station, currently served by (The plan says “Bayshore” and there’s no existing bus route that connects Baseline Station to Bayshore.) It’s currently being served by route 118.
  • Carling Avenue from Bronson Avenue to Carling O-Train Station. It’s currently being served by routes 6, 85, 101, 102.
  • Chapman Mills / Strandherd / Earl Armstrong from Barrhaven Centre to proposed Bowesville O-Train Station. Chapman Mills and Strandherd are supposed to be served by routes 94, 95 once the Strandherd-Armstrong bridge is completed.
  • Eagleson Road from Hazeldean Road to Highway 417. It’s currently being served by routes 96, 61, 62, 164, 168.
  • Hazeldean Road from Stittsville Main Street to Eagleson Road. It’s currently being served by routes 96, 118.
  • Innes Road and Blair Road from Millennium Station to Blair Station. It’s currently being served by routes 94, 121. 126, 128, 131.
  • Jeanne D’Arc Boulevard from Innes Road to Jeanne D’Arc Station. It’s currently being served by routes 30/130, 31/131, 132.
  • March Road from Carling Avenue to Maxwell Bridge Road. It’s currently being served by route 60.
  • Merivale Road from Baseline Road to Carling Avenue. It’s currently being served by routes 14, 151, 176.
  • Orleans Boulevard from Jeanne D’Arc Boulevard South to proposed Orleans Blvd LRT Station. It’s currently being served by routes 34/134, 132.
  • Richmond Road / Wellington Street West / Somerset Street from Woodroffe Avenue to Bank Street. It’s currently being served by route 2.
  • Robertson Road and Richmond Road from Eagleson Road to Baseline Road. It’s currently being served by routes 118, 97.
  • St Laurent Boulevard from Innes Road to Montreal Road. It’s currently being served by routes 114, 5, 7, 14.
  • Tenth Line Road from Charlemagne Boulevard to Regional Road 174. It’s currently being served by route 136.

To be clear, these transit initiatives are considered to be "affordable" and can be implemented by 2031. BRT projects are supposed to cost $317 million, while the transit priority projects (bus lanes, transit signal priority, etc) are estimated at $200 million, bringing the total cost to just under $3 billion.

Wednesday, October 9, 2013

Proposed transportation plan features light rail extensions to be completed by 2023



Mayor Jim Watson announced the City of Ottawa's proposed Transportation Master Plan this morning, and the ambitious plan includes light-rail extensions to Baseline, Bayshore, and Place D'Orleans, plus conversion of the O-Train to light-rail before adding in new stations on the current line and then extending the whole thing to Bowesville -- all happening concurrently, all finished before 2023, at a price tag of about $2.5B.

Here are the details of the mayor's speech from various city hall reporters and the mayor himself:


Not sure what that entails. It could mean better bus service connecting to the Confederation Line, since the college is not considered within walking distance from either Cyrville or Blair Station.


The new busways in the west are nothing new. Kanata North will likely see more reliable and less travel times for route 93 once the busway opens.

These "new bus measures in the east along Blair" are probably for route 94. Innes was mentioned as one of the "transit priority" roads in the city's media release. The others are Montreal Road, Hunt Club Road, Carling Avenue, and Bank Street. Transit priority usually means an adjustment of the traffic lights to minimize delays to transit vehicles.


The Airport Parkway will be expanded to four lanes total. The HOV lane will certainly improve service on the 97 route. Creating dedicated lanes act as an alternative to extending the O-Train to the airport. (As you'll see later, the O-Train line extends south of the airport, but doesn't connect to it.)


This benefits transit users in that area too because they'll now have access to either routes 16 or 18.


Plenty of discussion about the Richmond Underground already.


One of the proposed light-rail extensions is from Lincoln Fields to Bayshore Shopping Centre and here's how it's supposed to look:

So, it appears the Pinecrest-Bayshore busway, where routes 93 and 96 travel, will be converted into light-rail.


The O-Train south extension:
Interesting how there's an LRT extension to a rural area, but not to the airport. The additional ridership from the added stations and line extension can't be supported from the existing single track sections of the line. It would have to be expanded entirely to double-tracking eventually.

The new stations in the south will take some pressure off buses on the south-east Transitway, which is likely the goal here. To the north, the Gladstone O-Train station is a welcome addition.


Orleans LRT extension:

Most of the 95 bus line will be replaced in the east end and Orleans Boulevard Station will be a new station since there isn't an existing BRT one at the moment. One thing to note is the rail line will extend through the Greenbelt on NCC land, which is not something the crown corporation will easily give up.


This is supposed to be one large project, both physically and financially:







Hard to imagine all rail extensions would be constructed simultaneously within ten years, given that both federal and provincial governments are experiencing enormous budget deficits.


The new bold LRT plan is called "Stage 2":


The draft outline of the Transportation Master Plan can be seen on the city's website and further details are to be released later this afternoon by the city. The plan will be debated at a Transit Commission meeting next week, and at a Transportation Commission and City Council meetings in November.

Friday, October 4, 2013

uOttawa wanted its name on Lees LRT Station

If the University of Ottawa had its way, we would see "uOttawa - Canal" and "uOttawa - Lees" signs at LRT stations. According to the Citizen, the downtown university wanted both uOttawa and Lees LRT Stations to be named after the school.

The similar names can be confusing for new transit users and first-year Ottawa U students. Besides the school having an issue, there weren't any publicly known concerns raised with the name "Lees". The problem with naming it "uOttawa - Lees" is that Lees Ottawa U campus isn't the only destination the Confederation Line will serve. Existing high-rise apartments are in close proximity to the station and the city wants to intensify the surrounding area. Taking on the university's proposed name conflicts with the city's transit-oriented development goals, especially when the name of the school comes first.

Saturday, September 28, 2013

Construction update: Confederation Line western portal, Sept. 25

Digging has begun in earnest on the Confederation Line's downtown tunnel, as the city officially announced a few weeks back. Although potential damage to nearby heritage structures have raised some concerns, blasting continues, and thanks once again to Jim Louter, here are a few more photos of the of the ongoing project. All photos were taken on Sept. 25, 2013.

First, two photos from above the tunnel opening looking westward up the slope:



And below, two up-close photos of the trench's side wall: