OttawaLightRail.ca |
The official Confederation Line website was re-designed recently and is now providing updates on the construction progress.
Here's their update for this week:
West Portal
Central Shaft
- Removal of blasted rock and grubbing continues.
- Assembly of the first roadheader is completed.
- Blasting to excavate the ramp is completed.
- Excavation with hoe ram is scheduled to be completed by October 9.
East Portal
- Excavation continues.
- Installation of caissons continues for the foundation of the gantry crane
- Blasting at the central shaft is scheduled to begin by end of the week.
Highway 417
- Surface excavation of the construction ramp continues.
MSF
- Sewer and storm sewer work continues along the length of the highway.
- Advanced Traffic Management System (ATMS) work, including temporary poles and aerial wires, continues along the highway.
- Removals of retaining walls and bridge work continues along the highway.
- Demolition is scheduled to be completed by end of the week, with the exception of 737 Belfast Rd.
- Grubbing and material removal off-site continues.
1 comment:
ارخص شركة نقل اثاث
نقل عفش من جدة الى مكة افضل ارخص شركة نقل اثاث عفش من جدة الى مكة
شركة نقل عفش من جدة الى الامارات افضل شركة نقل شحن عفش من جدة الى الامارات دبي ابوظبي
افضل شركة نقل عفش من جدة الى الرياض افضل ارخص شركة نقل عفش اثاث من جدة الى الرياض
شركة نقل عفش من جدة الى الدمام افضل شركة نقل عفش اثاث من جدة الى الدمام الخبر
شركة نقل عفش من المدينة المنورة الى مكة افضل شركة نقل عفش اثاث من المدينة المنورة الى مكة
Post a Comment